Building 2 Week 2: 1st Floor Plastic Barrier Wall Up all week, Lead Abatement, Painting Entrance side of condos.
April 29, 2017 @ 8:00 am - 5:00 pm
Building 2 Week 2: 1st Floor Plastic Barrier Wall Up all week, Lead Abatement, Painting Entrance side of condos.
- 5/1 Monday
8:00 am – 12:30 pm Staging of Building 2, 1st Floor: Workers install plastic barrier wall enclosing and protecting walkway side of the building.
12:30 pm -3:30 pm Lead Abatement. 1st Floor Condos will NOT be accessible during this work due to lead dust. Plan on being out of the area during this time.
- 5/2 Tuesday
8:00 am – 3:30 pm Lead Abatement. 1st Floor Condos will NOT be accessible during this work due to lead dust. Plan on being out of the area during this time.
- 5/3 Wednesday
8:00 am – 3:30 pm Lead Abatement. 1st Floor Condos will NOT be accessible during this work due to lead dust. Plan on being out of the area during this time.
- 5/4 Thursday
8:00 am – 3:30 pm Painting of trim and sides of buildings. Condos will be accessible with some interruption from painting.
- 5/5 Friday
8:00 am – 3:30 pm Painting of trim and sides of buildings. Condos will be accessible with some interruption from painting.
- 5/6 Saturday – No Work
- 5/7 Sunday – No Work